The paving schedule proposed is:
Monday-Mill Veterans Way from Route 50 to Excelsior Ave
Monday-Mill York Street from High Rock Ave to Henry Street
Tuesday- Mill East Ave from McLaren Street to Excelsior Ave
Tuesday-Mill Clement Ave from Clinton Street to State Street
Wednesday- Pave Veterans Way from Route 50 to Excelsior Ave
Wednesday- Pave York Street from High Rock Ave to Henry Street
Thursday- Pave East Ave from McLaren Street to Excelsior Ave
Thursday- Pave Clement Ave from Clinton Street to State Street
Paving will begin at 6:00 am and should be completed by 2:00 pm. There is no parking of cars on the street during these hours and driveway access/egress will be limited with potentially lengthy delays.
Please note that depending on construction circumstances or changing weather conditions, this schedule could be revised. Thank You for your cooperation.