Posted on: June 3, 2019

[ARCHIVED] Paving-Week of June 17, 2019

DumpTruck

The paving schedule proposed is:

Monday-Mill Seward Street from Church Street to Clement Ave

Tuesday-Mill Wells Street from Church St to Waterbury Street

Wednesday- Pave Seward Street from Church Street to Clement Ave

Thursday- Pave Wells Street from Church St to Waterbury Street

Paving will begin at 6:00 am and should be completed by 2:00 pm. There is no parking of cars on the street during these hours and driveway access/egress will be limited with potentially lengthy delays.

Please note that depending on construction circumstances or changing weather conditions, this schedule could be revised. Thank You for your cooperation.