The paving schedule proposed is:
Monday-Mill Robinhood Court from Grand Ave through Robinhood Court Turn Around
Tuesday- Mill Hickok Road from Church Street to Greenfield Town Line (102 Hickok Road)
Wednesday- Pave Robinhood Court from Grand Ave through Robinhood Court Turn Around
Thursday- Pave Hickok Road from Church Street to Greenfield Town Line (102 Hickok Road)
Paving will begin at 6:00 am and should be completed by 2:00 pm. There is no parking of cars on the street during these hours and driveway access/egress will be limited with potentially lengthy delays.
Please note that depending on construction circumstances or changing weather conditions, this schedule could be revised. Thank You for your cooperation.