The paving schedule proposed is:
Tuesday- Mill Grand Ave from South Franklin Street & Elm Street
Tuesday- Mill Western Alley from Oak Street to Grand Ave
Tuesday- Mill Denton Road starting in the area of #12 Denton Rd through the address of #18 Denton Rd
Wednesday- Pave Grand Ave from South Franklin Street & Elm Street
Wednesday- Pave Western Alley from Oak Street to Grand Ave
Wednesday- Pave Denton Road starting in the area of #12 Denton Rd through the address of #18 Denton Rd
Paving will begin at 6:00 am and should be completed by 4:00 pm. There is no parking of cars on the street during these hours and driveway access/egress will be limited with potentially lengthy delays.
Please note that depending on construction circumstances or changing weather conditions, this schedule could be revised. Thank You for your cooperation.