The paving schedule proposed is:
Monday, June 27th MILL Warren Street from High Rock Ave to North St
Monday, June 27th MILL North Street from Circular St to Warren St
Tuesday, June 28th MILL Middle Avenue from East Harrison St to East Ave
Tuesday, June 28th MILL York Avenue from Pinewood Ave to East Ave
Wednesday, June 29th PAVE Warren Street from High Rock Ave to North St
Wednesday, June 29th PAVE North Street from Circular St to Warren St
Thursday, June 30th PAVE Middle Avenue from East Harrison St to East Ave
Thursday, June 30th Pave York Avenue from Pinewood Ave to East Ave
Street work is scheduled for the above street on the dates noted. Work will begin at 6:00 a.m. and should be completed by 4:00 p.m. There is no parking of cars on the street during these hours, and driveway access/egress will be limited with potentially lengthy delays. On the day of paving the road will be closed to all thru traffic until midafternoon. This notice is now distribute only through the City of Saratoga website service "Notify Me". To enroll to receive the notices to your email account or as a text message on your cell phone you can sign up at this web address: www.saratoga-springs.org/list.aspx Thank you for your cooperation.